Which of the following statements correctly describes the critical path?
a. It is the sequence of activities from start to finish in the network that have no float.
b. It consists only of activities with lag times.
c. The sequence of activities represents the shortest path through the project network.
d. It determines the latest possible end date of the project.



Answer :