A project has had a number of quality issues and has been escalated to management as a concern. What response should the project manager have the next time an issue is identified?
a) Invest more time in creating deliverables and allow the schedule and cost to shift.
b) Fix the issue immediately.
c) Escalate the issue.
d) Invest time in solving the root cause of the issue.



Answer :